SUPPLIER PROFILE

ARES Shield AI

Spacecraft protection systems

1 linked project1 supply / hosting record1 project-linked + 0 other1 contract / order record

Contract / order records are included in the total above. One record may cover several contracts or orders. Counts do not represent unique contracts or customers.

View these supply / hosting records in the relationship directory →

Project-linked supply & hosting

“Role confirmed” identifies a supplier or host without a separately disclosed contract. Dates refer to disclosures or supporting evidence, not necessarily signing dates. Details includes the role, buyer, qualifications and project milestones.

Project-linked supply and hosting. Each row is a catalog record. Expand Details for scope, qualifications, role and linked project milestones.
Project / organizationWork / contributionAgreement evidenceDisclosed valueDisclosure date
Lonestar data centersLonestar Data Holdings

AI-assisted sensing and nonkinetic high-power microwave protection for three Lonestar orbital-server satellites in the initial phase. Wider constellation protection is prospective.

Spacecraft protection systems

Details

Spacecraft protection systems

Role: Supplier. Provides the hardware or services described in this record.

Disclosed buyer: Lonestar Data Holdings

This record reports a contract or order. A record may cover more than one instrument and does not establish completed delivery.

ARES reports TRL 4 after laboratory tests. Orbital deployment and completed deliveries are not established. Wider constellation protection remains prospective. The signature date is undisclosed.

More than USD 5,581,180 (PLN 22 million). Latest issuer disclosure.

Value disclosure date: 8 Oct 2026

Evidence checked 13 Oct 2026.

Project: Lonestar data centers

Project stage: Demonstration program

Next project milestone: First StarVault payload is planned aboard LizzieSat-4 on SpaceX Bandwagon-6, alongside LizzieSat-5, no earlier than April 2027. Timing depends on qualification, integration and launch readiness.

This is a project target, not a supplier delivery commitment.

Contract / order disclosedMore than USD 5,581,180 (PLN 22,000,000)Source ↗