VALARIS 106
Valaris · Drilling rig · updated 18 July 2026
Now
- What is it doing?
- Contracted
- For whom?
- BP
- Where?
- Indonesia
- Until when?
- Jun 2028
Next
- Next assignment or transition
- No follow-on work identified
- Options
- 1 option row identified
- Downtime
- No planned downtime identified
Commercial outlook
- Classification
- Committed
- Estimated usable window
- Schedule not disclosed
- Confidence
- Source-reported
Visual schedule
BP
Indonesia
Jun 2025 – Jan 2026
FirmEvidence
- Source document
- Valaris Fleet Status Report
- Relevant excerpt
- VALARIS 106 KFELS MOD V-B 2005 BP Indonesia Jun 25 Jan 26 $95,000
- Publication date
- 4 May 2026
- Retrieval date
- 18 July 2026
- Confidence
- Source-reported
Open source Medco Energi
Indonesia
Apr 2026 – Jun 2026
FirmEvidence
- Source document
- Valaris Fleet Status Report
- Relevant excerpt
- Medco Energi Indonesia Apr 26 Jun 26 TCV of $5.4 million based on minimum duration of 45 days
- Publication date
- 4 May 2026
- Retrieval date
- 18 July 2026
- Confidence
- Source-reported
Open source BP
Indonesia
Jul 2026 – Jun 2028
FirmEvidence
- Source document
- Valaris Fleet Status Report
- Relevant excerpt
- BP Indonesia Jul 26 Jun 28 TCV of approx. $74 million based on estimated duration of two years. Four 1-well options
- Publication date
- 4 May 2026
- Retrieval date
- 18 July 2026
- Confidence
- Source-reported
Open source Technical profile
{
"design": "KFELS MOD V-B",
"buildYear": "2005",
"rigSubtype": "jackup",
"sourceSection": "Benign Environment Jackups"
}Change history
Contract awardedBP · Indonesia · firm Jun 25 – Jan 26
Historical baseline · detected 18 July 2026 ·
Source Contract awardedMedco Energi · Indonesia · firm Apr 26 – Jun 26
Historical baseline · detected 18 July 2026 ·
Source Contract awardedBP · Indonesia · firm_with_options Jul 26 – Jun 28